Benefits of OZbreak pile breaking
The benefits are as follows:
- No reinforcing bars are bent, cut or stretched, as is often seen when mechanical methods are used.
- No cracks, micro or otherwise, extend down into the pile head which would normally necessitate rework with hand held tools.
- No possibility of operatives applying injudicious force through either a machine mounted impact hammer, or carelessly placed pile breakers.
- No need for saw cuts around the perimeter of the pile to prevent over break.
Details
- Piles of all sizes can be broken in less than half an hour per pile.
- Instead of requiring manual demolition, creating significant rubble, as well as hand-arm vibration for employees, surplus concrete can be lifted mechanically using an excavator with minimum cleanup.
- OZbreak provides a clean break to the end of the pile, and the usual remedial work on the pile is not required.
Time
The following timeline illustrates the time savings which are available to construction contractors utilising OZbreak technology.
In this example 100 pile caps are broken in 1½ weeks compared with 7½ weeks for the conventional methods. A time saving of 6 weeks. Click on table for a larger view.